HS2 construction contracts priced at £19.5bn have already cost £26bn despite being “just over halfway done”, the boss of the high-speed rail project has told MPs.
Civil engineering to build tunnels and cuttings for the 100-mile line should be almost finished but is closer to 60% complete, while only a third of the wider project – including laying tracks and wiring – is done, the transport select committee heard on Wednesday.
Mark Wild, chief executive of HS2 Ltd, told the committee that the rush to start work in 2020 without balancing the risks in the contracts was the major reason for costs spiralling upwards.
Contracts were signed off in April 2020 and construction formally began five months later, before designs were finalised and local planning consents were in place, he said.
Wild, who started work last December, is currently engaged in a “reset” of construction, which he said would include reshaping his direct staff at HS2 Ltd, coming up with a credible schedule and budget, and renegotiating contracts in the autumn.
He said: “The bottom line is that, at the notice to proceed, the contractors could not price the risk. What we’re seeing is the crystallisation of risk: they should have cost £19.5bn, and we’ve already spent £26bn and we’re just over halfway done … Between 50% and 100% is the likely overspend.”
The line between London and Birmingham – initially designated phase one, but now the entirety of HS2 – was originally planned to open in 2026.
The schedule was subsequently postponed to between 2029 and 2033. But on Wild’s advice, Heidi Alexander, the transport secretary, told parliament last month that there was “no route” to full HS2 services until after 2033.
Wild said Covid and inflation caused by Russia’s invasion of Ukraine had both had significant impact on time and costs, but that HS2 had failed to manage costs.
He said the company was “unbalanced” and had “a significant gap” in its frontline workforce managing contractors, as well as having “too many consultants who’ve been there for too long”.
“We’ve ended up … locked in our own bureaucracy,” he added.
Also giving evidence, Lord Hendy said politicians had to be ultimately accountable for the decisions made. The rail minister told the committee it was unclear why political leaders had decided HS2 should be an “exceptionally fast railway”.
skip past newsletter promotion
Sign up to Business Today
Get set for the working day – we’ll point you to all the business news and analysis you need every morning
Privacy Notice: Newsletters may contain info about charities, online ads, and content funded by outside parties. For more information see our Privacy Policy. We use Google reCaptcha to protect our website and the Google Privacy Policy and Terms of Service apply.
after newsletter promotion
While accepting that higher speed did increase potential capacity, he added: “It is hard to understand why there was such zealotry about the highest-speed railway in a relatively small country.”
HS2 trains will have a maximum speed of 225 miles per hour, though Wild suggested last month they start running at lower speeds to reduce the period needed for testing and potentially run services sooner.
Wild told the committee he was confident that HS2 could “get a reset” in partnership with contractors who “are working across government and are part of a much bigger game than just HS2”.
With major contracts to be awarded on work such as the Sizewell C nuclear plant and upgrading the National Grid, Hendy said he believed firms would “lean in” to Wild’s plans.